Chapter 8 and the Red Book Explained: The Rules Behind Road Works

Chapter 8 and the Red Book Explained: The Rules Behind Road Works

Two documents set out how temporary traffic management should be done in the UK. People in the trade call them Chapter 8 and the Red Book.

Chapter 8

Chapter 8 is part of the Traffic Signs Manual, published by the Department for Transport. It is the main guidance on designing and running traffic management at road works, and the basis of the NHSS 12 layouts you learn on your courses. That is why many people call the work itself “Chapter 8 work”.

  • Part 1 (Design): 2009
  • Part 2 (Operations): 2009
  • Part 3 (Update): revised in March 2020 to reflect the 2016 Traffic Signs Regulations

The Red Book

The Red Book is the code of practice Safety at Street Works and Road Works. It covers signing, lighting and guarding for street works and road works on roads other than motorways and dual carriageways of 50mph or more, so it is the everyday rulebook for 12D and street works crews. The current edition dates from 2013.

A new Red Book is coming

In September 2026 the Department for Transport opened a consultation on an updated code, which closes on 14 December 2026. The draft would make the code statutory guidance. Trade press reports suggest the final version could be published in 2027. We will update this page when it is.

What it means for you

Your NHSS training teaches you the layouts and rules from these documents, and assessors check your work against them. When the new code is published, expect refresher training and employer briefings to cover the changes.